Mass tools multiply a volume by a density you can see. Heat tools stop at sensible heat or steady conduction. The worked case follows one small plant-room base and its contents.
A plant-room base, step by step
Step 1: concrete volume. A slab 4.5 m by 2 m by 0.2 m is 1.8 m³. Use concrete volume.
Step 2: concrete mass. At 2,400 kg/m³ that is 4,320 kg. Use mass from density. The density is an assumption; use the supplier’s figure if you have it.
Step 3: reinforcement. A 16 mm bar weighs about 1.578 kg/m. Twelve bars of 4.4 m are 52.8 m, or about 83.3 kg. Use rebar weight.
Step 4: a steel plate. A 2 m by 1 m by 10 mm baseplate at 7,850 kg/m³ is 157 kg. Use plate weight. These masses are what a lifting plan starts from, not the lifting plan.
Step 5: thermal movement. A 10 m steel pipe rack on the base, α = 12×10⁻⁶ per K, warms by 40 K and grows about 4.8 mm if free. If restrained, a force results that this page does not calculate. Use thermal expansion.
Step 6: heating a tank. 50 kg of water through 20 K at 4.186 kJ/kg·K needs 4,186 kJ. Over one hour that is about 1.16 kW. Use sensible heat.
Step 7: fabric loss. A wall of 40 m² at U = 0.28 W/m²·K with 20 K across it loses 224 W. Use fabric heat loss. Ventilation loss, thermal bridging and a change of phase are not included.
The chain at a glance
| Step | Result |
|---|---|
| Concrete | 1.8 m³, 4,320 kg |
| Rebar | 83.3 kg |
| Plate | 157 kg |
| Free movement | 4.8 mm |
| Tank heating | 1.16 kW for 1 h |
| Fabric loss | 224 W |
Where the chain stops
Each figure is the quantity named. None is a mix design, a lifting plan, a restraint design or a heat-loss calculation to a standard. Write the density, U-value or coefficient beside the result.
Putting the masses together
The concrete and reinforcement for the base come to about 4,320 + 83 ≈ 4,403 kg, or about 43.2 kN as a load on the ground beneath. If the base were precast and lifted, that mass, plus rigging, would be the starting point for the lifting plan. Cast in place, it is the starting point for the formation check in bearing screens.
Reviewing mass and heat figures
- Is the density right for the material and its condition, wet or dry, plain or reinforced?
- Are the units consistent: millimetres converted to metres, kJ to kWh?
- Does the heat figure include losses during heating, or is it the minimum energy?
- Is the U-value for the whole element, including frames and bridges?
- Is the thermal movement free, or is it restrained by fixings?
Questions
Why does reinforced concrete use 25 kN/m³?
Plain normal-weight concrete is about 24 kN/m³; the steel adds about 1 kN/m³ at typical reinforcement ratios. Use the figure the design basis states.
Can I add heat losses to the tank heating figure?
Yes. Estimate the average loss during heating and add the energy it removes over the heating time. For a well-insulated tank it is small; for an open tank it can be large.
Why is free movement useful if most members are restrained?
Because it tells you how much movement a joint or bearing must allow, or, if none is allowed, the strain the restraint must resist.
A second chain: a hot-water cylinder
A 200 litre cylinder holds about 200 kg of water. Heating it from 10°C to 60°C is a 50 K rise, so Q = 200 × 4.186 × 50 ≈ 41,860 kJ, or about 11.6 kWh. A 3 kW immersion heater needs about 3.9 hours to supply that energy, and longer in practice because the cylinder loses heat as it warms. The cylinder and water together weigh well over 200 kg, which matters for the floor or platform it stands on. A quick mass check belongs in the same note as the heat figure.
| Step | Result |
|---|---|
| Water mass | 200 kg |
| Heat for 50 K | 41,860 kJ (11.6 kWh) |
| Time at 3 kW | about 3.9 h before losses |
How accurate are the densities?
Typical densities are good to a few percent. Concrete varies with aggregate and moisture, steel hardly varies, and timber varies a great deal with species and moisture content. For a lifting plan, use certified weights or a margin set by the lifting engineer. For heat, the water figure is very reliable; for building materials, use manufacturers’ data where it exists.
Why convert mass to a load?
Ground, slabs and lifting gear are checked in kN, not kg. Multiply kilograms by 9.81 and divide by 1,000 to get kN: 4,403 kg is about 43.2 kN. Using kg as if it were kN is a factor-of-a-hundred error that a quick check against the expected order of the load will catch.
Related: Common calculations · Mechanical · Glossary · U-value from layers · Pre-mixed concrete bags · U-values and fabric heat loss
Sources
Last checked 14 October 2026. The logic is the textbook relationship named above. It is not a code check. See standards these tools do not replace.