Pre-mixed concrete bags calculator
How many bags for a small pour. Not a mix design and not a structural concrete specification.
Preliminary only. For structural concrete, follow the specification. Pre-mixed bags may not meet it.
Worked examples
EXAMPLE 1: Post pad
1.2 m × 0.6 m × 0.1 m = 0.072 m³. With 10% waste, 0.0792 m³. At an EXAMPLE yield of 0.011 m³ per bag, 7.2 → 8 bags, about 200 kg to carry.
EXAMPLE 2: Half a cubic metre
0.5 m³ with 10% waste is 0.55 m³ → 50 bags, about 1,250 kg. At this size, ready-mixed or a volumetric truck is usually more practical than bags.
Reading the result
Round up and keep a bag spare. Compare the total mass with what you can move by hand or vehicle; a large number of bags is a sign that another supply route would be better.
Use the concrete volume page first if you need the volume of a slab or cylinder.
Typical values
EXAMPLE bags per 0.1 m³ with 10% waste, for different printed yields:
| Yield per bag (m³) | Bags per 0.1 m³ |
|---|---|
| 0.010 | 11 |
| 0.011 | 10 |
| 0.012 | 10 (9.2 rounded up) |
Common mistakes
- Using a yield from a different product or bag size.
- Forgetting waste on uneven ground.
- Confusing dry volume of the bag with the yield of placed concrete.
- Using bagged concrete where the specification calls for a particular strength class.
- Ignoring manual handling limits.
How to use
Enter the volume in cubic metres, the yield per bag in cubic metres from the bag, a waste allowance in per cent and the bag mass in kilograms.
Edge cases
- Volume, yield and bag mass must be greater than zero; waste may be zero.
- The result is always rounded up to whole bags.
- Inputs over 10¹² are rejected.
Questions
What yield should I use?
The one printed on the bag. Products differ.
Is 10% waste enough?
For a formed pour on a level base, usually. Increase it for dug holes in uneven ground.
Can I use bags for a foundation?
Check the specification and building control requirements first.
Basis
This tool uses the formula shown under Method. It is standard arithmetic or physics and relies on no external data set or design standard, so check any values you enter against your own project data.
Last checked 17 October 2026. Preliminary figure only. See methodology and the disclaimer.