The calculators use textbook relationships. The standards below are where a design check actually lives. None of their text is reproduced here.
How to use this list on a project
Start from the project information requirements, not from this page. The requirements, the appointment and the specification say which document controls a decision. If two documents could apply, the project states the order. A list on a public site does not.
Name the document by its identifier and edition, and say which question it answers: a section check, a cable, a temporary-works procedure or an information-container name. Do not paste clauses into a model, a report or a file name. A short reference, plus the project’s own acceptance criteria, is what a review note needs.
Check that the edition is the one the project asked for, including any UK National Annex, amendment or project departure. A calculator here does not make that check, and a calculator result is not evidence that a standard has been applied. If the requirements are silent, ask the appointing party before the number is treated as design information.
Editions, as checked
Editions were checked against the publishers’ catalogues on 14 October 2026. Confirm against the publisher before relying on them; editions change.
| Document | Edition checked | Where this site stops |
|---|---|---|
| BS EN ISO 19650 series | Parts 1 and 2: 2018, Part 2 with the UK National Annex revised in 2021. Part 3: 2020. Part 4: 2022. Part 5: 2020. Part 6: 2025. Revisions of Parts 1 and 2 are in progress. | The file-name checker applies a project convention, not the annex. |
| Eurocode 2 and Eurocode 3 (BS EN 1992-1-1, BS EN 1993-1-1) | First-generation editions, with their UK National Annexes, remain applicable in the UK until 30 March 2028. Second-generation editions are published: BS EN 1992-1-1:2023 and BS EN 1993-1-1:2022. | Beam reactions stop at the moment; no section resistance. |
| Eurocode 7 (BS EN 1997-1) | BS EN 1997-1:2004+A1:2013 applicable until 30 March 2028. BS EN 1997-1:2024 published, with a UK National Annex. | Pad pressure is average load over area only. |
| BS 7671 (IET Wiring Regulations) | BS 7671:2018+A4:2026. The previous edition, incorporating A2:2022 and A3:2024, was withdrawn on 15 October 2026. | Voltage drop is a resistivity estimate. |
| BS 5975 (temporary works) | BS 5975-1:2024 (management procedures) and BS 5975-2:2024 (falsework), replacing BS 5975:2019. | This site cannot appoint a temporary works coordinator. |
| CIRIA Report 108, Concrete pressure on formwork | 1985. | Formwork pressure is the hydrostatic upper bound only. |
| Approved Document K (England) | 2013 edition. | Stair geometry reports pitch and 2R+G; it does not approve a stair. |
| Approved Document M (England) | Volume 1: 2015 edition incorporating 2016 amendments. Volume 2: 2015 edition incorporating 2020 and 2024 amendments. | Slope reports gradient; it does not approve a ramp. |
| DMRB, sewer-adoption guidance, FEH | Not checked here by edition. Use the version the drainage authority names. | Rational runoff is a screen. |
Buy the standard or use the publisher’s official guidance before a figure leaves the site.
How to cite a standard in a review note
A good citation names the document, its edition and the part that matters, and says what was done with it. For example: “Voltage drop screened at 20°C; cable selection to BS 7671:2018+A4:2026 by the electrical designer.” Or: “Pad pressure 178 kN/m² average, compared with the allowable 200 kN/m² in the ground investigation report; bearing design to BS EN 1997-1:2004+A1:2013 by the geotechnical designer.” The note is short, but it tells the reader what has and has not been checked.
When editions change
Standards are revised and amended. A project normally fixes the editions in its specification or appointment, sometimes at a date, so that a change part-way through does not alter the design basis without a decision. When a new edition is published, check whether the project has adopted it, whether there is a transition period and whether any withdrawn edition is still named in the project documents. The Eurocode transition to 2028 is an example where both generations exist at once.
Questions
Can I quote a figure from a standard?
Short references, such as an identifier and a clause number, are normal. Reproducing tables or substantial text is not, because the text belongs to the publisher. This site points to where a figure lives and leaves the figure there.
Why are some editions not listed?
Where the edition could not be checked against the publisher, such as for some drainage guidance, the table says so rather than guess.
Where are the sources?
The editions were checked against BSI, ISO, the IET, CIRIA and GOV.UK catalogue pages on 14 October 2026. See the editorial policy for how sources are chosen.
Who keeps this table up to date?
The Eng Hub reviews it when an edition changes; see the checked date below.
Does a withdrawn standard become wrong?
Not automatically. It is no longer current, but a project may still be contracted to it. Check the project documents before changing the design basis.
Related: ISO 19650 in plain English · Temporary works · Electrical limits · Glossary
Last checked 14 October 2026. Original guidance. Standards text stays with the publisher.