Same rise and run, four ways of saying the slope. Useful for ramps, drainage falls and setting-out checks.

Worked examples

Example 1: Gentle fall

0.15 m rise over 3 m: 5%, 2.86°, 1 in 20.

Example 2: Steeper ramp

0.5 m over 6 m: 8.33%, 4.76°, 1 in 12.

Reading the result

Run is horizontal distance, not the sloping length.

Approved Document M sets ramp limits that depend on the length of each flight. Check the current edition for the limit that applies.

Drainage falls are often written as 1 in N, road and ramp gradients as percentages, and roof pitches in degrees. The page gives all three so the same number can be checked against any drawing.

Typical values

1 in NPercentage / angle
1 in 128.33% / 4.76°
1 in 205.00% / 2.86°
1 in 402.50% / 1.43°
1 in 801.25% / 0.72°

Common mistakes

  • Using the sloping length as the run.
  • Confusing percentage with degrees: 10% is about 5.7°, not 10°.
  • Dropping the sign, so a fall reads as a rise.

How to use

Enter the rise and the horizontal run in metres. The result is the gradient as a percentage, an angle and a ratio “1 in N”.

Edge cases

  • The run must be greater than zero. A negative rise is allowed and shows a fall.
  • A rise of zero gives a level surface: 0% and no “1 in N” ratio.
  • Run is horizontal distance, not the length along the slope. On steep slopes the difference matters.

Questions

What is 1 in 12 as a percentage?

About 8.33%, or 4.76°.

How much does a 2.5% fall drop over 40 m?

1.0 m.

How do I convert a percentage back to “1 in N”?

Divide 100 by the percentage. 5% is 1 in 20, 2% is 1 in 50 and 8.33% is 1 in 12. For angles, the gradient is the tangent of the angle, so 1 in 20 is tan⁻¹(0.05) ≈ 2.86°. Write the gradient the same way the drawing or specification does, so the check is like for like.

Does the slope tool give a ramp length?

No. If you know the rise and the gradient you want, the run is rise divided by gradient: a 0.5 m rise at 1 in 15 needs 7.5 m of horizontal run, before landings are added. Check the landing and flight limits in the guidance the project uses.

Basis

This tool uses the formula shown under Method. It is standard arithmetic or physics and relies on no external data set or design standard, so check any values you enter against your own project data.

Last checked 14 October 2026. Ramp limits sit in Approved Document M (England): Volume 1, 2015 edition incorporating 2016 amendments; Volume 2, incorporating 2020 and 2024 amendments. Worked figures are scenarios. See methodology and the disclaimer.