Temporary works coordinator: the BS 5975 process explained

BS 5975-1:2024 describes a procedure: a temporary works coordinator, a design brief, a design check, and a permit to load or strike. A website cannot appoint that person. The formwork tool here is only the hydrostatic upper bound, unit weight times height of fluid concrete.

Worked bound

25 kN/m³ over 3 m is 75 kN/m². CIRIA Report 108 will often give a lower design pressure because pour rate and temperature limit how fluid the concrete remains. Using 75 kN/m² as a design pressure can overstate the load. Using it as permission to omit the design is worse.

Excavation volume on this site is a prism. Batter, trench support and a striking time are not in it. Those belong in the temporary-works design, not in a browser field.

Scope: this guide covers where the formwork and excavation tools stop. The procedure itself is in BS 5975-1:2024; falsework design is in BS 5975-2:2024.

What the procedure is for

Temporary works fail when nobody owns them: a prop is removed early, a design assumption is not passed to site, or a change is made without a check. The procedure in BS 5975-1 answers that with named roles, a register of temporary works, a design brief, a design, an independent design check of a rigour that matches the risk, and formal permission to load and to strike. None of those can be done by a calculator. The figures on this site can help a designer see the order of a load quickly; they cannot replace the brief, the design or the check.

From pressure to force

The hydrostatic bound grows linearly from zero at the top of the pour to its maximum at the base. For 3 m of fluid concrete at 25 kN/m³ the base pressure is 75 kN/m², and the total force on one metre of wall face is half of 75 × 3, or 112.5 kN. If the ties are on a 0.9 m by 0.9 m grid, a tie near the base carries a tributary area of 0.81 m², about 60.8 kN on the bound. That is why tie capacity and spacing are a design matter, and why the full bound is worth knowing before a pour rate is chosen.

Fluid height (m)Base pressure at 25 kN/m³Force per metre of face
1.025 kN/m²12.5 kN
2.050 kN/m²50 kN
3.075 kN/m²112.5 kN
4.5112.5 kN/m²253 kN

Excavations

The earthworks tool treats an excavation as a rectangular prism. A trench 30 m long, 0.6 m wide and 1.5 m deep is 27 m³ in place. Battered back at 1:1 to a 0.6 m base, the same 1.5 m deep trench is 3.6 m wide at the top, with a cross-section of 3.15 m², and the volume rises to about 94.5 m³. Whether to batter, step or support the sides is a temporary-works decision based on the ground, groundwater, surcharge from plant and spoil, and the time the trench stays open.

Questions

Can I use the hydrostatic bound as the design pressure?

It is conservative for most normal pours, so a designer may choose to use it. The point is that someone competent chooses, records the choice and checks the formwork for it. The bound is not a reason to skip the design.

Who decides how rigorous the check must be?

The procedure sets categories of check that depend on the complexity and risk of the temporary works, and the temporary works coordinator makes sure the right category is used. Read the current edition for the categories and their requirements.

What a design brief should carry

  • What the temporary works must do, and for how long.
  • The loads, including concrete pressure assumptions, pour rate and construction loads.
  • The ground information, existing structures and services nearby.
  • Access, sequence and any constraints on striking or removal.
  • Who will check the design and who will issue permission to load.

A brief that states the pour rate and concrete type lets the designer decide whether the hydrostatic bound or a lower design pressure applies.

What does a permit to load mean in practice?

It is a formal confirmation, by the person authorised in the procedure, that the temporary works have been built as designed and checked and are ready to take load. Before a pour, that usually means an inspection of the formwork, ties, props and bracing against the drawings. A permit to strike works the same way in reverse, after the concrete has gained enough strength.

Does a small job need the procedure?

The procedure scales with the risk, so even simple temporary works need someone responsible and a proportionate check.

Tools: hydrostatic formwork pressure, earthworks volume.

Related: Slab prop load screen · Excavation quantities

Sources

Last checked 14 October 2026. Editions: BS 5975-1:2024, BS 5975-2:2024, CIRIA Report 108 (1985). Original guidance. Standards text stays with the publisher.