BS 5975, the UK code of practice for temporary works, is now in two parts. BS 5975-1:2024 covers how temporary works are managed and controlled. BS 5975-2:2024 covers the design and use of falsework. Both are dated 31 December 2024, and BSI announced them on 25 February 2025. Together they replace BS 5975:2019. BSI lists both parts as current.
Temporary works do not make headlines often, but this revision affects anyone who designs, checks, coordinates or supplies falsework. This post sets out what BSI says has changed, where HSE’s guidance fits, and how a quick prop-load figure relates to the new Part 2.
Why the standard was split
BSI says BS 5975:2019 was divided to make it easier to use. Sections 1 and 2 of the 2019 code became Part 1, and Section 3 became Part 2.
- BS 5975-1:2024, management procedures. This is guidance on the procedural controls for temporary works on any construction project. It includes recommendations on training and on making sure temporary works are conceived, designed, specified, built, used and dismantled safely and under control.
- BS 5975-2:2024, falsework design and implementation. This covers the design, specification, construction, use and dismantling of falsework. Falsework is the temporary structure that supports a permanent one until it can carry itself. BSI says this is the first full revision of the falsework design content since 2008.
Part 2 is aimed at temporary works designers, temporary works coordinators, suppliers, manufacturers and contractors. It can also be applied to other temporary works, not only falsework.
What changed in Part 2
BSI’s product page lists the main changes. In summary:
- Limit state design is included, alongside permissible stress design, which has been kept and revised. BSI notes that the loads stated are unfactored. They conform to BS EN 1991-1-4 and BS EN 12812, and can be taken as characteristic values for limit state design.
- Wind. Maximum wind forces are now based on a likely erection period of one year, not two as before, with a ten-year return period. There is new guidance on wind near tall structures, funnelling by terrain or buildings, and susceptibility to vortex shedding.
- Class A falsework. The structural design of Class A falsework, as defined in BS EN 12812 and excluded from its design scope, now includes limit state methods.
- Simplified methods kept and revised. This applies to simplified methods for deriving loads, such as wind loads, and to the increased factors used for member design when those methods are used.
- Analysis of different systems. Methods for top-restrained, partially braced and fully braced systems have been kept and revised.
- Back-propping. The method for working out how much load passes through flat slabs as back-propping has been revised.
The terms and definitions have been updated, and the information in clause 5 has been reordered. We do not reproduce the new methods or values here. They belong to the standard.
Where HSE’s guidance fits
HSE’s temporary works guidance sets out the legal duty. Any temporary structure must be designed, installed and maintained to withstand foreseeable loads, and used only for the purpose it was designed for. Temporary works such as scaffolding, excavations, cofferdams and caissons must be inspected regularly by a competent person.
HSE also says that there are no specific legal requirements on how temporary works are managed. Instead, it describes formally appointing a temporary works coordinator as an effective approach. The coordinator should have authority to stop work, and in all but the simplest cases a design with calculations will be needed. Part 1 of BS 5975 is the detailed code of practice for that management system. HSE’s guidance and the standard support each other. Neither replaces the other.
A worked example: the first number, not the design
Before any falsework design, someone usually asks how much load each prop will carry. Our prop-load estimate gives an unfactored figure for an interior prop on a regular grid.
EXAMPLE
A 300 mm slab is cast on props at 1.2 m × 1.2 m centres. The calculator’s example inputs are: fresh concrete 26 kN/m³, formwork self-weight 0.5 kN/m² and construction load 1.5 kN/m².
- Slab: 0.300 × 26 = 7.8 kN/m². Total area load: 7.8 + 0.5 + 1.5 = 9.8 kN/m².
- Tributary area: 1.2 × 1.2 = 1.44 m². Load per prop: 9.8 × 1.44 = 14.11 kN, unfactored.
- Open the grid to 1.5 m × 1.5 m and the tributary area becomes 2.25 m². The load rises to 22.05 kN per prop, which is 56% more.
This figure is a starting point for a conversation with the temporary works designer. It is not a falsework design. The formwork and construction loads above are the calculator’s example inputs, not values taken from BS 5975-2. The calculator does not check prop capacity, extension or eccentricity. It does not cover wind, lateral stability, edge or end props, or the foundation under the base plates. It also does not deal with back-propping through the floors below, which is the area Part 2 has revised. Each of those checks can govern.
What to check on a live project
- Edition references. Temporary works procedures, design briefs and checking certificates should cite BS 5975-1:2024 and BS 5975-2:2024, not BS 5975:2019.
- The design philosophy. State whether a falsework design uses limit state or permissible stress design, and do not mix factors between the two.
- Wind assumptions for falsework that stands for a long time or sits near tall buildings, given the revised wind guidance.
- Back-propping in multi-storey flat-slab frames. The method has been revised, so do not reuse older calculations without a review.
Our existing temporary works guide explains why a quick pressure or prop figure is not a design. This post records the change in the standard.
Illustrative only. Not design advice.