BS 7671:2018+A4:2026 is now the only current version of the IET Wiring Regulations. The IET and BSI published Amendment 4 on 15 April 2026 and said it could be used straight away. They set the withdrawal of the previous version, BS 7671:2018+A2:2022+A3:2024, for six months after publication, which was 15 October 2026. The overlap has now ended.
This post sets out what changed, according to the IET’s own announcements, and what the change means for the screens on this site. It does not reproduce the text of the standard. If you design, install, inspect or test, you will need your own copy of the amended book.
The timeline
- 15 January 2026. The IET and BSI signed off the content of Amendment 4. They said it could be used as soon as it was published, and that the previous version would be withdrawn six months later.
- 15 April 2026. BS 7671:2018+A4:2026 was published and went on sale. From this date, either version could be used.
- 15 October 2026. Six months after publication, BS 7671:2018+A2:2022+A3:2024 was withdrawn.
BS 7671 is the UK national standard for new low-voltage installations, for additions and alterations to existing installations, and for periodic inspection and testing. Amendment 3:2024 is now part of the main document, not a separate insert. So a single volume, BS 7671:2018+A4:2026, is the reference.
What changed, in the IET’s words
The IET’s announcements list four main areas, plus smaller changes throughout the book.
A new chapter on stationary secondary batteries
This chapter covers batteries used to store energy and supply an installation, with or without solar PV. According to the IET, it deals with system design, power conversion equipment, bidirectional and hybrid inverters, and whether protective devices suit energy flowing in both directions. That last point matters for vehicle-to-home and vehicle-to-grid set-ups. The chapter also puts weight on where the battery goes, ventilation and fire risk.
A new Section 716 on Power over Ethernet
Section 716 covers Ethernet cabling that supplies extra-low-voltage DC to equipment such as LED lighting and small devices. It relies on SELV and PELV for protection against electric shock. Section 716 sits in Part 7, which can modify the general rules. The IET says it limits SELV and PELV to 60 V ripple-free DC in dry locations and 15 V ripple-free DC in all other locations. That is lower than the usual 120 V DC. Connections must comply with BS ISO/IEC 11801-1 and be able to carry a continuous 750 mA per contact.
Functional earthing for ICT
A new section covers functional earthing and functional equipotential bonding for information and communication technology equipment and systems. Functional earthing exists so equipment works properly, not for shock protection.
A major revision of Section 710, medical locations
Medical locations are now classed as Group 0, 1 or 2. Group 2 locations, such as operating theatres, need a medical IT system. It uses a transformer and an insulation monitoring device so the supply carries on through a first fault and staff get a warning before a second fault would disconnect it. Two independent supplies and a UPS are also needed, placed as close as possible to the equipment they serve. The IET says this brings the UK into line with IEC 60364-7-710:2021. The amendment also adds a schedule of test results for recording the resistance of supplementary protective equipotential bonding conductors.
The IET also says the amendment takes in further CENELEC harmonisation documents and IEC standards. The detail of those changes is in the book, not in the announcements, so we do not summarise it here.
A worked example at extra-low voltage
Lower-voltage DC circuits are a theme of this amendment, through PoE and battery systems. Voltage drop is one reason they need care: the same drop in volts is a much bigger share of a small supply. Our voltage-drop estimate shows this with simple inputs.
EXAMPLE
A two-core copper run carries 1.5 A over a one-way length of 30 m. Each conductor is 0.5 mm². The calculator doubles the length for the go-and-return loop and uses copper resistivity at about 20°C.
- Loop resistance: 1.72×10⁻⁸ × 60 ÷ 0.5×10⁻⁶ = 2.064 Ω.
- Drop: 1.5 × 2.064 = about 3.1 V.
- On a 48 V supply, that is 6.45%. On 230 V, the same 3.1 V is 1.35%.
The current, the length and the cable are all the same. Only the supply changes, and the percentage is almost five times larger. Try your own figures in the voltage-drop calculator.
This is a resistive estimate for a generic two-core run. It is not a PoE design. PoE uses twisted-pair data cable, with power shared over more than one pair. The cable and connector limits, the power-sourcing equipment and the device rating all decide whether a link works. Amendment 4 did not change the general approach to voltage drop as far as the IET’s announcements say, and nothing here should be read as a new limit. For the deemed-to-satisfy values, read Appendix 4 of the current book.
What it means for this site
Where our electrical pages refer to BS 7671, they now mean BS 7671:2018+A4:2026. The calculators give the same results as before. They are preliminary physics estimates: resistance, current, power and voltage drop. They do not do the checks in the regulations, such as current-carrying capacity, fault protection, disconnection times or the special-location rules above. Those stay with the designer and the current book.
If you keep certificates or design notes, check that they name the edition and amendment the work was designed and inspected to. Work that started before the withdrawal date may have used the earlier version. The IET’s page on keeping up to date with BS 7671 lists the current edition and its key dates.
Illustrative only. Not design advice.