A preliminary take-off of dig, haul and fill, in the order you usually need it. The numbers are EXAMPLE figures; site data and the model replace them.
Quantities only. Nothing on this page decides whether an excavation is safe, whether a trench needs support or what batter is stable. Those are temporary works and geotechnical decisions.
Start with what the number is for
An excavation quantity answers one of three questions. How much ground is dug in place, which is what an excavator moves and what most rates are measured against. How much loose material leaves site or goes to a stockpile, which sets lorry numbers and tip costs. How much fill is needed to make up levels or backfill a trench, which sets imports. Each uses a different volume, and most errors in early estimates come from mixing them up.
Keep three columns from the start: in place, loose and compacted. Then each conversion is a visible factor rather than an assumption buried in a single figure.
Simple prisms: strips, pads and reduced levels
For a rectangular strip with an average depth, the in-place volume is length × width × depth. The earthworks volume calculator does exactly this and applies a bulking factor for the loose volume. EXAMPLE: a 30 m × 8 m strip at 0.6 m average depth is 144 m³ in place, 180 m³ loose at a bulking factor of 1.25.
The weak point is the average depth. On anything other than a level site, take levels on a grid, work out the depth to formation at each node and average them with the weighting your grid method uses. The deepest point alone overstates the volume, sometimes by a lot.
Trenches
A trench is a long prism with a trapezium section. With base width b, depth d and side slope n horizontal to 1 vertical on each side, the area is d(b + nd). Vertical, supported sides have n = 0. The trench excavation calculator gives the in-place volume, the loose spoil and the backfill after deducting the pipe.
EXAMPLE: 30 m of trench, 0.6 m wide and 1.5 m deep with vertical sides, gives 27 m³ in place and 33.75 m³ loose at 1.25. A 160 mm pipe takes up 0.60 m³, leaving about 26.4 m³ of bedding, surround and backfill. Batter the same trench at 1:1 and the dig rises to 94.5 m³, with a top width of 3.6 m. That comparison is often the first hint that trench support, or a narrower working method, will save money on a constrained site. It does not tell you whether the sides will stand; that is for the temporary works design.
Split long runs where the invert depth changes. One average depth for a sewer that runs from 1.2 m to 3.5 m deep hides a large error. Add separate allowances for manholes, chambers, sumps and over-dig.
Linear schemes: cut and fill by end areas
Roads, embankments and channels are taken off from cross-sections at a regular spacing. The average end area method takes the mean area of two adjacent sections and multiplies it by the distance between them, separately for cut and fill. The cut and fill calculator does one pair of sections at a time.
EXAMPLE: sections 20 m apart with cut areas of 12 and 8 m² and fill areas of 0 and 3 m² give 200 m³ of cut and 30 m³ of fill, a surplus of 170 m³ in place. Repeat for every strip and add the totals.
The method assumes the area changes in a straight line between sections. It overstates the volume where the shape changes a lot, and it is weakest where cut runs out to zero and fill begins. Closer section spacing, the prismoidal formula with a mid-section, or a surface-to-surface volume in the model are the usual refinements. For a final balance, the model volume is normally the better figure; the end-area result is a check that the model is roughly right.
Bulking and shrinkage
Dug material occupies more space than it did in the ground. The ratio of loose to in-place volume is the bulking factor. Indicative ranges are around 1.10–1.15 for sand and gravel, 1.25–1.35 for topsoil, 1.30–1.40 for firm clay and 1.50–1.70 for blasted rock. These are illustrative only; use site investigation data or the contractor’s experience on similar ground.
Compacted fill usually occupies less than its loose volume and can be less than its in-place volume. That is a separate shrinkage or compaction factor. Do not apply bulking to the fill requirement: if you need 100 m³ of compacted fill, you buy or win more than 100 m³ loose.
Balancing and what the balance hides
A cut surplus on paper is not necessarily usable fill. Topsoil is stripped and stored separately. Material that is too wet, too soft or contaminated may be classed as unsuitable and has to go off site, while the same volume of fill is imported. Take unsuitable material out of the cut column before balancing, and keep topsoil in its own line.
Where the material is moved also matters. A balance across a long scheme can still involve long hauls or crossing a watercourse. A mass-haul diagram, which this site does not provide, is the usual tool for that.
A short checklist
- State whether each figure is in place, loose or compacted.
- Record the bulking and shrinkage factors and where they came from.
- Split trenches by depth and deduct pipes using the outside diameter.
- Use a section spacing that suits the ground and the alignment.
- Separate topsoil and unsuitable material.
- Check the totals against the model before relying on them.
Where this stops
None of these figures is a design. Excavation safety, trench support, batter stability, groundwater control and the effect of spoil heaps near an edge sit with the temporary works coordinator and designer, as described in temporary works. The quantities simply give everyone the same starting numbers.
Related tools: Trench excavation · Cut and fill · Earthworks volume · Slope and gradient · Setting-out logic
Sources
Last checked 17 October 2026. Bulking ranges are indicative, not from a standard. Original guidance. Standards text stays with the publisher.