Cut and fill calculator (average end area)

Volumes between two sections. Not a mass-haul diagram and not a surface-to-surface model volume.

Preliminary quantities only. Bulking, shrinkage and unsuitable material are not included.

Worked examples

EXAMPLE 1: Cut section running into fill

L = 20 m. Cut 12 and 8 m², fill 0 and 3 m². Cut = 20 × (12 + 8)/2 = 200 m³. Fill = 20 × (0 + 3)/2 = 30 m³. Net surplus 170 m³ in place.

EXAMPLE 2: Change from cut to fill

L = 25 m. Cut 5 and 0 m², fill 0 and 6 m². Cut = 62.5 m³, fill = 75 m³, net shortfall 12.5 m³. Where an area drops to zero, a short pyramid-like wedge is formed and the end-area result is an approximation.

Reading the result

The volumes are in place. Before balancing, multiply cut by a bulking factor for haulage and allow for the fill shrinking when compacted. Material classed as unsuitable cannot be reused and should be taken out of the cut before balancing.

Add the strips between each pair of sections along the route to get the totals. Section spacing is commonly 10 m, 20 m or 25 m on linear schemes; closer spacing is needed on curves and where the ground changes quickly.

Typical values

EXAMPLE run of three sections at 20 m spacing with cut areas of 12, 8 and 2 m²:

StripAreas (m²)Cut volume (m³)
Ch 0–2012 and 8200
Ch 20–408 and 2100
Total300

Common mistakes

  • Mixing the cut and fill areas of one section into one number.
  • Using chainage values instead of the distance between sections.
  • Balancing in-place cut against compacted fill with no factors.
  • Spacing sections too widely on curves or uneven ground.
  • Forgetting topsoil strip, which is usually handled separately.

How to use

Enter the distance between the two sections in metres and the cut and fill areas at each section in square metres. Enter 0 where a section has no cut or no fill. Repeat for each pair of sections and add the results.

Edge cases

  • Distance must be greater than zero; areas may be zero but not negative.
  • Where an area falls to zero between sections the result is an approximation.
  • Curved alignments need a correction for the centroid offset, which is not applied.
  • Inputs over 10¹² are rejected.

Questions

Is average end area accurate enough?

For a preliminary take-off, usually. For payment or a final balance, use the model or the prismoidal method.

What is the prismoidal formula?

V = L/6 × (A1 + 4Am + A2), where Am is the area at the mid-section. It needs an extra section.

Why does my net volume not match the model?

The model uses the surfaces directly. The end-area method assumes straight-line change between sections.