Pipe velocity and head loss explained

Velocity tells you whether a straight pipe is in a familiar band. Many building-services water lines are talked about around 1 to 2 m/s. That is a habit, not a specification. Head loss tells you the straight-pipe cost of that velocity. Fittings can exceed it.

Worked pipe

0.02 m³/s in a 150 mm internal bore is about 1.13 m/s. With a friction factor of 0.02 over 50 m, Darcy–Weisbach head loss is about 0.44 m. The same bore, 40 m long at 100 mm, holds 314 litres. Those two results do not size a pump or a support.

What is missing

Roughness was not looked up. Bends, valves and tees are absent. Temperature, lining and a minimum velocity for self-cleansing are absent. A pipework design still needs the project specification and a competent check.

Scope: this guide is about reviewing a pipe size and its losses. For the step-by-step calculation chain from flow to pump power, see fluid logic.

Velocity against bore

For a fixed flow, velocity falls with the square of the diameter and straight-pipe loss falls faster still. The table keeps 0.02 m³/s, f = 0.02 and 50 m of pipe, and changes only the bore.

Bore (mm)Velocity (m/s)Head loss over 50 m (m)
1002.553.31
1251.631.08
1501.130.44
2000.640.10

Going from 150 mm to 100 mm multiplies the loss by about seven and a half. Going up to 200 mm cuts it to a quarter but costs more pipe, more water to fill and lower velocity, which matters for flushing and, in drainage, for self-cleansing. The friction factor was held constant here for clarity; in reality it changes a little with velocity and bore, so a design would recalculate it for each size.

Fittings: the loss people forget

Each fitting loses roughly K × v²/2g, where K is a loss coefficient from the manufacturer or a recognised data source. At 1.13 m/s, v²/2g is about 0.065 m. A modest run with six elbows (K about 0.75 each), two open gate valves (about 0.2 each), one tee through the branch (about 1.5) and an exit loss (1.0) has ΣK ≈ 7.4, so the fittings lose about 0.48 m. That is more than the 0.44 m lost in 50 m of straight pipe. The K values used here are typical orders of magnitude only; real values depend on the fitting’s geometry and size.

A review checklist

  • Is the bore the internal diameter of the actual pipe material and pressure class, not the nominal size?
  • Is the friction factor justified from the Reynolds number and the pipe roughness, or is it a guess?
  • Are fittings, valves, strainers and equipment pressure drops included in the total head?
  • Is the velocity in a range the project specification accepts, considering noise, erosion and, for drainage, self-cleansing?
  • Does the volume held in the pipe matter for filling, draining, water quality or heat-up time?

Questions

Is there one correct velocity?

No. Lower velocities reduce noise and loss; higher velocities reduce pipe size and cost. Projects usually state a range for each service. Treat any figure you hear as a habit until you find it in the specification.

Why does the loss matter if the pump can cope?

Every metre of head the pump overcomes costs energy for the life of the system. On the worked duty, 0.92 m of combined loss is about 6% of the 15.44 m total head and the same share of pump power.

Nominal size and bore

Plastic pressure pipe is usually sold by outside diameter and SDR, the ratio of outside diameter to wall thickness. A 110 mm SDR 11 pipe has a wall of 10 mm and a bore of about 90 mm. At 0.005 m³/s, the velocity in that bore is about 0.79 m/s. Using 110 mm as the bore would give about 0.53 m/s, a third too low, and would understate the friction loss by much more. A 63 mm SDR 11 pipe has a bore of about 51.5 mm. Check the bore from the manufacturer for every material and pressure class used.

Does pipe roughness change over time?

Yes. Scale, corrosion and biofilm increase roughness and reduce the bore, so the friction loss in an old pipe can be much higher than in a new one. Designs often allow for this with a higher roughness value or a margin on head. When checking an existing system, measured pressures and flows are better than assumed values.

Should I size for future flow?

If the brief says so. Oversizing for a future that never comes lowers velocity, which can hurt water quality and flushing. A stated future load is a design input; an assumed one is a guess, so record which it is.

Tools: velocity and head loss, pipe volume.

Sources

Last checked 14 October 2026. Original guidance. Standards text stays with the publisher.